Skip to main content
Mirror and Move Sticky Notes

Delve into the steps for displaying sticky notes on multiple boards

Updated over a week ago

Mirror Sticky Notes

Using the mirror function allows you to visualize the same sticky note on multiple boards. For instance:

  • You can visualize a Feature on the ART Planning Board, the Team Board and also on the Solution Planning Board

  • A Dependency is visualized on both Team Boards, on the ART Planning Board and in case you're having a cross-ART dependency it makes sense to visualize the Dependency also on the Solution Planning Board

  • You can visualize a Risk on the Team Board and at the same time bring it up the ART PI Risk Board using the mirror function.

To allow users to mirror sticky notes to other boards, make sure that you've configured it accordingly in the RTE Cockpit.

Visualizing Features on ART / Solution Planning and Team Boards

Initially a Feature (ART-level work item) is visualized on the ART Backlog Board (see primary board)

To mirror a Feature on to the ART Planning Board

  1. Assign it to a Team (this will automatically visualize the Feature on the ART Planning Board)

To mirror a Feature on to a different Board

  1. Select the Sticky Note

  2. Click the Mirror button either on the sticky note or in the action bar

  3. Select the Board on which you want to visualize the sticky note

Visualizing Dependencies across Boards

  1. Create a Dependency on Team Board A

  2. Click "Dependent on" and select a Team in your or a different ART to share the dependency

  3. Select the dependency

  4. Click the Mirror button either on the sticky note or in the action bar

  5. Select the Board on which you want to visualize the dependency

Visualizing team-level sticky notes on other Boards

  1. Select the User Story

  2. Click the Mirror button either on the sticky note or in the action bar

  3. Select the Board on which you want to visualize the user story

Move Sticky Notes

With the move functionality you can remove a sticky note on one board and visualize that sticky note on another.

  1. Select a Sticky Note

  2. Click on the "Move" button on the sticky note action toolbar

  3. Select the Board you want to move the sticky to

Be careful in case the sticky note is synced with an ALM-tool. See Impact in case of ALM-Connection

Impact in case of ALM-Connection

Jira

A duplicate of that sticky note (issue) is created in Jira and the existing issue will be moved to your team backlog

Azure DevOps

The area path of that sticky note (work item) is changed

Rally

The project of that sticky note (work item) is changed

Did this answer your question?