ART Risk Board Overview
The ART PI Risk Board then becomes indispensable when it comes time to resolve (R.O.A.M) all the risks in a broader management context. Use the ART PI Risk Board to review risk (Team or ART level) one by one; the risks are discussed and decisions can be made into one of the following categories:
Resolved – The teams agree that the risk is no longer a concern
Owned – Someone on the train owns the risk since it cannot be addressed during PI planning
Accepted – Some items are simply facts or potential problems that must be understood and accepted
Mitigated – Teams identify a plan to reduce the impact of the risk
© Scaled Agile, Inc. Include this copyright notice with the copied content
Move or Mirror a Team Risk sticky note to the ART PI Risk Board
There are two options on how you can bring a Team Risk onto the ART PI Risk Board
Move the Team Risk
The "Move" action is available by default in case you defined the Sticky Type Function as "Risk"Mirror the Team Risk
If you want to allow users to mirror Team Risks onto the ART Risk Board this must be configured under the Team Board config in the RTE Cockpit
Impact on Team Board when moving mirrored Risk on the ART PI Risk Board
In case you're ROAMing a Risk on the ART PI Risk Board that was mirrored from the Team Board, the ROAM attribute will be updated accordingly.